Brunswick Tram Depot Upgrade

March 2024 - December 2026

The Department of Transport and Planning (DTP) and Yarra Trams are upgrading the Brunswick Tram Depot to support the addition of larger trams to the fleet, additional trams in the depot and provide improved accessibility and safety.

Works are continuing into 2027 as we build the new tram terminus on Cameron Street and complete work to connect the new subtation to the depot stabling yard. 

Upcoming works:

Cameron Street works extension 

We need to extend the closure of Cameron Street to complete this work and connect the new substation to the depot stabling yard.

We thank the community for their patience while we complete these works.

What’s happening?

  • Completing the terminus track to provide increased operational capacity.

  • Tunnelling underneath Cameron Street and the shared use path to connect the electrical supply from the new substation to the depot stabling yard.

  • Upgrading tram signalling and overhead wires.

What to expect?

  • The large vehicle detour will remain in place via the Council car park for access into Cameron Street.

  • Tinning, Prowse, Cozens and Peveril streets will be open during our works.

  • Cameron Street will be open from Moreland Road to Peveril Street.

  • The Upfield shared use path will continue to detour via Colebrook Street.

  • Noise levels will be mostly low to medium with short periods where noise levels may increase to high when we install track and complete tunnelling. High noise activities will be scheduled during the day.

  • Works will take place during the day. If out of hours works are required, we'll let you know in advance.

  • Businesses located around the works will remain open. Please continue to support local business during these essential works

  • Emergency services access will be maintained.

Moreland Road High Voltage Feeder Cable works

We will be installing underground high-voltage feeder cables in November and December. This involves directional boring and cable hauling between the Yarra Trams car park on Colebrook Street and the Moreland Station car park on Cameron Street.

When?

  • 7am to 7pm, Monday 16 November to Wednesday 13 January (excluding weekends)

What to expect?

  • There will be temporary partial car park closures within the Moreland Station car park. All DDA parking spaces will be retained.

  • Low to medium levels of noise, while we complete excavation.

  • Increased construction vehicles in the area

Cameron Street and Sydney Road cable hauling

In January 2027, we’ll be installing electrical cables to connect the new Brunswick Tram Depot substation to the tram network.

When?

Cameron Street:

  • 9pm to 11am, Friday 8 and Saturday 9 January 2027

  • 1am to 5am, Sunday 10 to Thursday 14 January 2027

Sydney Road:

  • 9am to 5pm, Tuesday 12 and Wednesday 13 January 2027

What to expect?

  • Low to medium levels of noise while construction vehicles move around the works area.

  • Parking lane and footpath closures outside the tram depot on Sydney Road.

  • No impacts to bus or tram services.