As part of the modernisation of Melbourne's tram network, Yarra Trams and Public Transport Victoria are renewing tram tracks at the intersection of Victoria and Church Streets in Richmond.

The curved tram tracks within the work-zone are about 40 years old and require renewing.  The renewed tracks will deliver a better road surface for cyclists and tram passengers, produce less tram noise due to potholes, broken railes and wheel squealing, and will be quicker to repair in the future due to the use of new semi resilient materials.

Timings

Preliminary track renewal work

Preliminary work will begin on Wednesday 5 April 2017 and will involve the unloading and pre-welding of rails.

Major track renewal work

Major work will occur at the intersection of Victoria and Church Streets in Richmond.  Works will commence at 12:01 am on Satuday 8 April and will continue 24 hours a day until 5 am on Tuesday 11 April 2017.

Tram passengers

Route 12, 78 and 109 tram services will be affected.  For more details closer to the time, please visit yarratrams.com.au/servicechanges.

Motorists

Due to the nature of works, there will be a number of road closures in place from 12:01 am on Saturday 8 April until 5 am on Tuesday 11 April 2017:

  • Victoria and Church Street will be closed between Albert Street and Fairchild Street
  • Church Street will be closed between Princes Street and Baker Street

Detours will be in place for the duration of the works.  Traffic controllers will be in place to direct traffic and help facilitate local access where needed.

Pedestrians

The work zone will be fenced off for safety, however, footpaths will remain open to allow pedestrian access to all businesses located around the work zone.

Noise and dust

Associated noise and dust from machinery, vehicles and work crews is unavoidable, but Yarra Trams will do all it can to keep this to a minimum.  The noisiest work will occur between 6 am and 10 pm, however, there may be a need to conduct noisy work outside these hours to ensure that the work is completed by 5 am on Tuesday 11 April 2017.

We advise that this work is being performed in accordance with our obligations to Public Transport Victoria and is necessary to maintain a safe tram network as required by the Rail Safety Act 2006 (Vic).

For more information visit ptv.vic.gov.au or call 1800 800 007 6 am - midnight (all night Friday & Saturday).